Estimating a project's earned and final duration

International Journal of Project Management(2016)

引用 25|浏览5
暂无评分
摘要
Using standard Earned Value Management (EVM) protocols, the current approach to Earned Schedule (ES) is extended and formalized to establish its rigorous, theoretical foundation. A precise definition is provided for what we term the project's earned duration, whose creation completes the triad of planned, actual, and earned durations. The published ES formula emerges as a linear approximation, but is found to work with some nonlinear cost profiles, and the conditions under which it gives both correct and incorrect duration estimates are noted. In the several planned and earned value functional profiles examined, no approximations are required to derive an exact analytical expression for the final duration; most duration formulas are straightforward and useful. The reliability and accuracy of the duration formulas are demonstrated with several examples of real, nonlinear project data that represent large classes of projects. We conclude with practical guidance for project managers.
更多
查看译文
关键词
Earned value management,Earned schedule,Duration estimation,Schedule variance
AI 理解论文
溯源树
样例
生成溯源树,研究论文发展脉络
Chat Paper
正在生成论文摘要